A network has been crashed to the point where all activities are critical. additional crashing:

A network has been crashed to the point where all activities are critical. Additional crashing OA. can be done, but all critical tasks must be reduced in duration. O B. may require crashing multiple tasks simultaneously O C. is prohibitively expensive. O D. is impossible E. is unnecessary. A network has been crashed to the point where all activities are critical. Additional crashing OA. can be done, but all critical tasks must be reduced in duration. O B. may require crashing multiple tasks simultaneously O C. is prohibitively expensive. O D. is impossible E. is unnecessary.

The correct option is
B- May require crashing multiple tasks simultaneously
When too many activities are running then you may to close the
running activities forcefully. This will make the system fast as
there will be fewer activities. Free up system is the key to handle
this situation